Spurstowe Terrace – Hackney

Contract Value – £139,000.00

Start Date – Sept 2011          

End Date – April 2012

Works undertaken:

  • Access Control
  • Sky+, IRS, Turksat, Hotbird
  • AOV Smoke Shaft
  • Mains Distribution including Ryefields Boards
  • External Street Lighting
  • Undercroft Lighting
  • Communal Lighting and Power
  • Undercroft Lighting
  • Flat Lighting and Power
  • Drawings and Design Work
  • O+M Manuals

A new build development consisting of 34 flats split across 2 blocks. Block A had 17 socially rented 1, 2, 3 & 4 Bed Flats. Block B had 17 Shared Ownership 1, 2 & 3 Bed Flats. We were responsible for all works after the incoming supply. This meant running 240m 4 Core Cables to feed Block A via under-ground Ducts. We were responsible for the design of all aspects of electrical work on the project including the mains distribution AOV ventilation systems and external lighting lux level design’s.